Construction of 12No. Mechanised Boreholes at Hohoe
Not Completed Hohoe, Hohoe Municipal, Volta Water, Works And Housing
No photos yet.
About this project
Construction of 12No. Mechanised Boreholes at the Hohoe Constituency
Construction of 12No. Mechanised Boreholes at the Hohoe Constructionituency
12
Scope
50%
Progress
Project location
Open larger map · approximateProject impact
Positive
- 12 delivered
- Beneficiaries: Residents of Hohoe
Evidence & sources
No public sources attached yet. This record is shown with an unverified status. Know more about this project? Tell us →
Related projects
More in Water, Works And Housing
Government Service DeliveryCompletedPremix Fuel Automation Project at Mepe
North Tongu District, Volta
Completed 2023Fisheries
Water, Works And HousingCompletedGoG Affordable Housing Programme
Tema West Municipal, Greater Accra
Completed 2017Housing & Works
Water, Works And HousingNot Completed
2020 National Flood Relief Programme
Nation Wide
40% complete
40% completeHousing & Works
Water, Works And HousingCompletedKumasi Road and Drainage Extension Project (KRDEP)
Asokwa Municipal, Ashanti
Completed 2021Road Infrastructure