HomeProjectsMapSectorsAsk
NPP logoThe NPP RecordGhana's delivery, in evidence
OverviewTimelineMetricsProjectsProgrammesRegionsSectorsBeneficiariesJobsVideosAsk a Question

All Projects

Search and filter government projects across Ghana

20 projects found

Construction of 1No. Bungalow for DCE

Nabdam District, Upper East
Water, Works And HousingCompleted
2023
completed

Drilling of 5No. Boreholes at some selected communities in Nabdam.

Nabdam District, Upper East
Water, Works And HousingCompleted
2020
completed
Construction of 10 Seater Water Closet Toilet with Mechanized Borehole at Nangodi Market

Construction of 10 Seater Water Closet Toilet with Mechanized Borehole at Nangodi Market

Nabdam District, Upper East
Water, Works And HousingCompleted
2020
completed
Siting, drilling and mechanization of 4No. Electric powered with 5,000L capacity tank mounted on an elevated stand at  Pelungu.

Siting, drilling and mechanization of 4No. Electric powered with 5,000L capacity tank mounted on an elevated stand at Pelungu.

Nabdam District, Upper East
Water, Works And HousingNot Completed
35%
complete

Siting, drilling and mechanization of 4No. Electric powered with a 5,000L capacity tank mounted on an elevated stand at Zalerigu.

Nabdam District, Upper East
Water, Works And HousingNot Completed
35%
complete
Construction of Mechanized Solar Powered Water System

Construction of Mechanized Solar Powered Water System

Nabdam District, Upper East
Water, Works And HousingNot Completed
50%
complete
Construction of Mechanized Solar Powered Water System at Nangodi

Construction of Mechanized Solar Powered Water System at Nangodi

Nabdam District, Upper East
Water, Works And HousingNot Completed
50%
complete

Sitting and drilling of 12No. Boreholes fitted with hand pumps at twelve (12) communities in the district

Nabdam District, Upper East
Water, Works And HousingNot Completed
51%
complete

Sitting, drilling and mechanization of 1no. Solar powered with 5,000l capacity tank on an elevated stand at logre putin

Nabdam District, Upper East
Water, Works And HousingNot Completed
36%
complete
Construction of Mechanized Solar Powered Water System at Damol-tindongo

Construction of Mechanized Solar Powered Water System at Damol-tindongo

Nabdam District, Upper East
Water, Works And HousingNot Completed
50%
complete
Construction of 10 Seater Water Closet Toilet with Mechanized Borehole at Kongo Market

Construction of 10 Seater Water Closet Toilet with Mechanized Borehole at Kongo Market

Nabdam District, Upper East
Water, Works And HousingNot Completed
90%
complete
Construction of 10 Seater Water Closet Toilet with Mechanized Borehole at Pelungu Market

Construction of 10 Seater Water Closet Toilet with Mechanized Borehole at Pelungu Market

Nabdam District, Upper East
Water, Works And HousingNot Completed
90%
complete

Construction of 10 Seater Water Closet Toilet with Mechanized Borehole at Zanlerigu SHS

Nabdam District, Upper East
Water, Works And HousingNot Completed
90%
complete
Siting and drilling of 2No. Boreholes fitted with hand pumps at Meehiboug.

Siting and drilling of 2No. Boreholes fitted with hand pumps at Meehiboug.

Nabdam District, Upper East
Water, Works And HousingNot Completed
50%
complete
Construction of 10 Seater Water Closet Toilet with Mechanized Borehole at Asonge Community

Construction of 10 Seater Water Closet Toilet with Mechanized Borehole at Asonge Community

Nabdam District, Upper East
Water, Works And HousingNot Completed
90%
complete
Construction of community center with a hall, store, an office and unit 2-bath and toilet each at Asonge.

Construction of community center with a hall, store, an office and unit 2-bath and toilet each at Asonge.

Nabdam District, Upper East
Water, Works And HousingNot Completed
45%
complete
Construction of 10 Seater Water Closet Toilet with Mechanized Borehole at Sakote Township

Construction of 10 Seater Water Closet Toilet with Mechanized Borehole at Sakote Township

Nabdam District, Upper East
Water, Works And HousingNot Completed
90%
complete
Construction of Mechanized Solar Powered Water System at Gane-Asonge

Construction of Mechanized Solar Powered Water System at Gane-Asonge

Nabdam District, Upper East
Water, Works And HousingNot Completed
50%
complete

Mechanized Solar Powered Water System at Sakoti

Nabdam District, Upper East
Water, Works And HousingNot Completed
50%
complete

Siting, drilling and mechanization of 4No. Electric powered with 5,000L capacity tank mounted on an elevated stand at Asonge.

Nabdam District, Upper East
Water, Works And HousingNot Completed
35%
complete
The NPP Record

A national achievement evidence platform — presenting the delivery record of NPP governments with data, maps and verified sources.

Explore
  • Projects
  • Metrics
  • Jobs
  • Achievements
  • Videos
  • Regions
  • Sectors
  • Beneficiaries
  • Timeline
Engage
  • Ask a Question
  • Track a submission
  • Report a correction
© 2026 The NPP Record. Data from the Ghana Delivery Tracker.